Vestas has received a 42 MW order from Vind AX in Finland, for the Langnabba wind project which is aiming for completion in Q1 2022. The project will see ten V136-4.2 MW turbines installed from Q3 2021 onwards. Vestas has secured a 74 MW order across two of Ilmatar Energy’s wind farms in Finland. The Voimamylly wind project will use six 4.3 MW turbines, while the Rasakangas wind project features eight 6.0 MW turbines – a debut for Vestas onshore turbines of this size. Both are set to see deliveries from Q3 2021, with commissioning expected in Q1 2022. Orsted is expected to sell 25% of its 1,100 MW Ocean Wind offshore wind farm, which is currently in pre-consent stages…