As Release 15 is finalized, operators are already impatient for Rel16

No sooner than 3GPP had announced the completion of its Release 15 standards for 5G, than some operators and vendors were starting to look ahead to Release 16, which should be finalized in late 2019. This is not only a marketing ploy – it reflects the fact that, as in previous mobile generations, the first release does not address all the operators’ requirements. Indeed, many of the most potentially powerful weapons that 5G will put in the hands of service providers, such as dynamic spectrum support, dense device-to-device communications, and extreme reliability, will have to wait for Release 16 or even beyond.

This does not take away from the achievement of getting Release 15 largely completed on time. Of course, there will be gaps, which the 3GPP working groups will continue to address throughout the rest of the year, but the foundations are in place for a broad ecosystem of standardized equipment and devices, and just as importantly, there are initial specifications for the 5G Next Generation Core (5G NGC).

More than 600 delegates from operators, network, terminals and chipset vendors, internet companies and vertical industry players met in La Jolla, USA, for the final freezing of the standards.

Georg Mayer, chair of 3GPP TSG CT (technology specifications group – core and terminals), said: “Two years ago, 5G was seen as a vision or even just a hype – with the closing of Rel-15, 3GPP has made 5G a reality within a very short time. The outcome is an amazing set of standards that will not only provide higher data rates and bandwidth to end customers but which is open and flexible enough to satisfy the communication needs of different industries. 5G will be the integration platform for heterogeneous businesses.”

However, this has not been a simple release, thanks to the AT&T-driven push to have a subset of the radio network standards – 5G New Radio Non-Standalone (5G NR NSA) – defined on a fast-track basis, so that operators with particularly urgent timescales would be able to deploy as early as late 2018, without having to take the risk and expense of a pre-standard or semi-proprietary route (like Verizon’s). NSA, which can only operate with a 4G core, was finalized in March this year, and now the release is complete with the addition of NR Standalone (which runs with the 5G-NGC).

That still leaves a certain fragmentation of the platform however. Some operators will choose to deploy NSA for some years to come, either to get that headstart (Standalone kit will take another 9-12 months to be fully available), or because they want to continue to use the 4G core, postponing the disruption and expense of implementing the new core. In some cases, that is because the 5G cells will be just in-fill for a predominantly 4G network; in others, because the operator does not want to deploy the new core until key surrounding technologies, like Network Functions Virtualization (NFV), are more mature.

A GSMA Intelligence report last year noted that the economies of a Standalone deployment would be “significant” for a national roll-out, but these would be achieved only after the MNO has made a major upfront investment, since Standalone “is likely to prove more expensive at least in the early stages”.

So while some regard NSA as almost a US-specific technology, created for the convenience of AT&T, it is likely to have a longer shelf life, and more international applicability, than that.

Nonetheless, many operators – especially the European majors, which are generally more cautious about 5G timing than peers in north America and east Asia – say they would prefer to be in less haste, and wait to deploy the 5G RAN and core together. Orange, for example, has been vocal about the trade-offs of investing in an NSA network, whose performance and flexibility will be limited by the 4G core; and then having to upgrade later to Standalone.

However, Orange is now testing both technologies and has not made a firm decision on how to proceed, acknowledging that SA does bring additional complexity because of the changes to the core. “Changing the core will be pretty complex with IT and integration issues,” Emmanuel Lugagne Delpon, SVP of Orange’s Lab Networks, told Light Reading. “The easier path is to do non-standalone with the existing [4G] vendor.”

However, that could just be storing up complexity problems for later, when the operator decides to migrate to the 5G-NGC. “This is an issue for the whole industry because there are different paths and we haven’t yet defined what path we need to select for moving from non-standalone to standalone,” said Delpon. “Step one is pure capacity, while step two is to change the architecture of the core, put computing power at the edge of the network and virtualize. That is where the transformation will provide the platform for new use cases, but it is a huge transformation.”

But while only China Mobile, among the early 5G movers, has publicly said it will not deploy NSA at all, the option of moving straight to 5G SA will become more common as the platform stabilizes and for MNOs with longer launch timescales. The majority of MNOs (almost 70%, according to the Rethink survey) are prepared to wait until Standalone is fully available, the economics have become clearer, the spectrum allocated, and there are plenty of devices – and in the meantime, make do with enhancing LTE.

The timing of availability of major elements of the broader 5G platform is, therefore, complicated, and will affect each operator’s capex cycle, its potential opex savings, and the services and business models it can support in the first wave of its 5G roll-out. A recent survey of over 75 MNOs worldwide by Rethink Technology Research identified the following profiles of deployment of 5G between 2019 and 2023, which we see as the first phase of the new platform.

These are:
1. Deploy NSA and stick with it for several years, keeping the 4G RAN and core as the primary network.
2. Deploy NSA to get a headstart in selected regions or services, but transfer to SA as soon as its ecosystem is stable (the two are fully interoperable). SK Telecom, NTT Docomo and AT&T are in this group.
3. Deploy NSA and stick with it in order to deploy a more mature, more fully virtualized core and RAN in a few years’ time. This will rely on enablers from Release 16, especially further work on the different functional splits which 3GPP is defining for vRAN; and also on standards emerging from ETSI or the open source telco virtualization community, to support, for instance, interoperable management and orchestration (MANO).
4. Deploy SA and 5G-NGC from the start of deployment, though potentially not until the early 2020s, because there is limited urgency to deploy 5G, and the total cost of ownership will be better if an operator waits for the ecosystem to mature and implements only one set of specifications
5. Deploy SA and 5G-NGC from the start of deployment, though with varying timelines, in order to support new types of use cases at an early stage. Release 15 has been mainly focused on enhancing performance to support the traditional mobile broadband services, so many of the capabilities which will be needed for emerging Internet of Things (IoT) applications will have to wait to be fully developed until Releases 16 and 17.

Some operators will fall into multiple categories for different types of roll-out. For instance, AT&T has already outlined NR Standalone tests and plans; but in some areas and use cases it will not upgrade until the virtualized core is more stable.

Hank Kafka, AT&T’s VP of architecture and standards, said in an interview: “AT&T’s announced deployments will use the NSA architecture and standards to enable tight integration and smooth interworking between LTE and NR. As the capabilities of 5G devices and the 5G-NGC become more advanced, we will continue to evaluate NSA and SA configurations and deploy those that best support the enhanced mobile and fixed wireless broadband experience for our customers.”

He continued: “The initial NSA option 3, defined as part of this week’s Release 15 completion, uses LTE and the EPC, and provides the fastest way for us to deploy NR and provide enhanced mobile broadband services to our customers. Further NSA options to be completed this December will continue using LTE and introduce the 5G-NGC. Over time, virtualization enables deploying a network that can support multiple options.”

In category 5 comes China Mobile, among others. The Chinese market leader expects to be the first operator to deploy a Standalone network at large scale, starting in 2020. It is just embarking on field trials in Shanghai, Hangzhou and three other cities, with at least 100 base stations deployed in each. It will also run smaller scale trials in a dozen other cities, including Beijing and Shenzhen.

Most of the trials will run in 3.5 GHz, with some in 4.9 GHz. Initially the equipment will be pre-standard and will be software-upgraded once standardized equipment is available. The MNO is targeting new, as well as traditional, use cases right from the start. It said in a statement last week: “China Mobile will release the first version of its 5G commercial product requirements this year and launch the first pre-commercial terminals in 2019.” With these, it will target not just fixed and mobile broadband, but also some of the emerging 5G use cases such as smart manufacturing.

The Chinese national 5G initiative, the IMT-2020 Promotion Group – which aims to get homegrown technologies into the standards – is already verifying and evaluating future Release 16 specifications. This R&D and testing program, which supports all three Chinese MNOs, is now in its third phase.

Huawei said last week that it had taken the “momentous step” of testing and verifying a series of functions based on the current state of Release 16 work, and targeting all three of 5G’s use case categories – enhanced mobile broadband (eMBB), massive machine-type communication (mMTC) and ultra-reliable low latency communications (URLLC).

According to Huawei, some of the key technologies on which the Chinese effort is focused are:

• For eMBB: Type II codebook optimization, multiple codes and feedback enhancement.
• For mMTC: 5G NR uplink video transmission; 5G-enabled AI for performance and security in dense environments such as university campuses.
• For URLLC: 5G NR V2X solutions – Huawei tested an end-to-end system with coordinated design of cellular V2X with a roadside unit and mobile edge computing. The 5G NR Uu air interface (for end points) and NR Sidelink (a dedicated link between vehicles) were both implemented in the tests.

Latest Chinese 5G tests embrace Massive MIMO and dual connectivity:

Back in Release 15, China Mobile has worked with Intel and Huawei on its latest 5G NR tests, reaching a data transfer rate of 1.5Gbps in C-band spectrum – the first choice in China for initial 5G roll-out – using Massive MIMO with beamforming.

The operator said this was the first multivendor 5G NR test using full protocol, full channel and full procedures, though still based on NSA. The test was conducted at the China Mobile Research Institute (CMRI) using the largest 3.5 GHz) cell bandwidth defined by 5G NR and with an 128-antenna array (64×64).

“The success of this interoperability test can provide more kinds of terminals for the follow-up China Mobile 5G scale test,” said Huang Yuhong, VP of CMRI.

Meanwhile, Nokia has demonstrated a 5G Dual Connectivity as part of a government trial. The call took place using 5G NR in the 3.5 GHz band and LTE in the 2.1 GHz band, supported by a 5G user equipment simulator provided by Prisma Telecom Testing.

Using dual connectivity (which was standardized for LTE in Release 12 but scarcely implemented), a device can consume radio resources from two or more different base stations, connected with non-ideal backhaul, while the terminal is in RRC_CONNECTED mode. This has similar benefits to those of carrier aggregation, but without the need for co-siting. DC supports a split bearer concept, in which a data bearer is split between the two base stations, at the PDCP layer. The PDCP layer at the anchoring user plane node is responsible for the PDU numbering, distribution between master and secondary base stations, aggregation, sorting and in-sequence delivery to the upper layer.