UK startup Moixa and Hitachi have announced a collaboration to build a smart grid, on an island off the southwest of England. This smart grid will combine renewable energy, battery storage and electric vehicles to balance power and usage in the Isles of Scilly – a Cornish archipelago. The project will involve building a virtual power plant (VPP) on the island using solar power and battery storage, while also integrating vehicle to grid (V2G) storage into the same network.
The project is the first announced of its kind, and will act as testing grounding and model for a holistic VPP system that utilize all the assets of emerging clean power technology – which in this case, heavily center around solar power, due to the remote location.
The two companies, along with a few other partners, are being mainly funded by the EU, with a $13.13m budget. PassivSystems will supply home energy management systems (HEMS), while Moixa contributes both software and smart batteries.
Riot spoke to Chris Wright, Moixa’s CTO, who explained that aside from installing batteries on the island, Moixa would also be designing a software system to manage V2G connections and storage networking across the island, using the company’s existing Grid Share software as a framework.
This is made possible by the fact that EV chargers are bi-directional meaning that they can be used to both charge and discharge vehicles – giving EVs the ability to be a storage asset on the grid, to store excess solar or to move energy from the batteries and back into the grid.
Most residential battery storage units have between 4-15kWh of capacity. A typical EV, in contrast, has anywhere between 40-100kWh of storage capacity. EV battery capacity currently goes unutilized as a storage asset, due to the lack of V2G integrations, but have the potential to manage considerably more electricity than a typical residential storage unit.
Wright outlined how the software system would be faced with several management challenges, when determining how much of the EV’s battery can be used as a storage asset on the island’s VPP. The primary concern of a driver is their ability to drive their car, the Grid Share software must ensure that a driver has enough power to undertake any potential journeys – which on the Isles, are admittedly going to be pretty short trips.
The EV’s battery charge state needs to be factored into a driver’s patterns of usage, as well as any random incidents of usage where a driver decides to make extra journeys outside of their normal routine – before any capacity on the battery can be considered a grid asset. The customer outrage when their car is effectively unusable is something that needs to be avoided by such projects.
Consequently, usage behavior is the determining factor behind how much storage capacity can be considered as a grid asset. The Grid Share software would collect journey data before using machine-leaning techniques, to build basic models of driver usage behavior.
Testing such a V2G system on a small island has its advantages. With only 9-miles of roads, EVs are less likely to be traveling extended distances, meaning more time the batteries can be used as a storage asset.
Static storage has proven a tough sell so far. Collectively, the two largest battery storage companies in the residential market, Sonnen and Tesla, completed 22,000 installations globally. In contrast, the total global EV stock hit 2m units last year and looks set to grow even further as a wider range of cheaper EV models entre the market.
Developing models that incorporate EV batteries as grid storage assets offers a solution to the huge lack of storage capacity and flexibility that aging grid infrastructure is currently faced with. Successful V2G platforms will thus become increasingly important as an increased number of EVs hit the showrooms – otherwise a grid is forced to install static storage, at its own expense, when it could instead use the dynamic vehicle storage via partnerships.
Moixa already offers its residential battery storage customers the opportunity to opt into a grid sharing scheme, which pays them an annual fee of £50 so the company can compete for grid service ancillary contracts – agreements between the network operator and any company that assist with frequency regulation on the grid.
EVs could offer their owners access to these sorts of schemes too, and the higher battery capacities might mean higher potential payments – for car owners that are happy to leave their cars plugged in, to act as grid storage, in exchange for money or credits from their utility.