India’s government is biting off more than it can chew, proposing a total deployment of smart meters across the country in just three years. All the evidence suggests that much like the Smart City Mission project, delays are inevitable.
The government has set a target of replacing all conventional energy meters in the country with smart meters by the end of 2022. This roll out would have to reach the almost 300 million households in India, as well as all buildings used for retail, agriculture and industry.
We just can’t see hundreds of millions of smart meters rolling out across the country in such a short timeframe, and the lack of a detailed plan from the government makes this drive seem even more hopeless.
Riot has come to realize that such technology announcements from India should always be taken with a large pinch of salt. As the government’s Smart City Mission showed, a lot of money is needed to even scratch the surface of a country as vast and diverse as India. Small drives at state level also indicate that this target will not be met.
So, what has sparked this drive? The government’s Union Budget, delivered this week, has allocated just over $3bn to the energy sector, with two main aims – modernizing the ways DISCOMs (distribution companies) operate, primarily through smart meter deployment, and pushing the expansion of solar.
Shailendra Dubey, chairperson of All India Power Engineers Federation, estimated the renewal of all smart meters will cost around $12.6bn, yet the government has only set aside around one quarter of that for their entire energy initiative – and some of this is supposedly being spent on solar installations.
Finance Minister Nirmala Sitharaman said that “the distribution sector, particularly the DISCOMS, are under financial stress. I urge all the States and Union Territories to replace conventional energy meters with prepaid smart meters in the next three years.” Sitharaman argued the switch to smart meters would benefit both the utilities and consumers.
It seems the announcement has instigated some movement at state level.
Uttar Pradesh’s (UP) state government has set a target of installing around 4mn smart meters in the state by March 2021.
Going on the fact that there were 33mn households in UP in 2011, this roll out would only impact roughly 10-15% of households in the state. There are currently around 900,000 smart meters installed in UP, so far more smart meters are needed, far more quickly, if national targets are going to be met.
Uttar Pradesh Power Corporation Ltd’s (UPPCL) President, Arvind Kumar, said the corporation sees smart meter roll out as a means of “bridging the company’s revenue gap and checking power theft.” Rumors are that the UPPCL plan to roll out smart meters initially in cities with a population of 1mn or more.
As for which smart meters will be used, this entirely depends on who is responsible for the roll out. Private smart meter projects in India tend to favor RF mesh networks, and while the state-owned Energy Efficiency Services Limited (EESL) often champions cellular networks, there are still no Licensed LPWANs up and running in India.
Reliance Jio planned to launch the first nationwide Cat-NB network in January this year, but here we are in February with no network – yet another example of the delays which we have come to expect in India.
Considering the rapid roll-out intended by the government, it seems likely that the EESL will be the ones oversee this – it’s hard to imagine private companies having much incentive to work so quickly. It therefore seems likely that these meters will operate on licensed cellular networks, when they finally arrive, instead of waiting for additional networking infrastructure to be built.
As we have seen from Prime Minister Modi’s Smart City Mission, the government tends to overstate the speed at which modernization initiatives can occur. Implementation of the Smart City Mission has been an uphill struggle, to say the least
The Smart City Mission was launched in 2015 with the objective of creating 100 ‘smart’ (a term which the mission itself left undefined) cities by 2020. However, as of July 2019, the project had received $14bn in funding, but only 933 smart city projects had been completed – just 18% of all projects proposed, in India’s somewhat piecemeal approach to implementing a complete smart city. In that program, small projects inside the city are funded, with the vision of eventually creating a fully functioning smart city, however, this approach seems to be proving to be very fragmented.
Why is this relevant? Modernizing Indian infrastructure is a mammoth task, and it seems the government is often too indulged in quickly responding to campaign promises and global pressures with strong commitments and targets that are rarely met.
With regards to the government’s solar targets, we noted in July last year how India is struggling to get off coal. The country continues to build coal plants due to astronomically cheap labor costs and a relative indifference towards climate change.
As such, multiple auction prices for renewable energy are set out of reach of all but the most ambitious solar and wind players, as India needs to match its own low local levelized cost of energy (LCOE) of coal with future renewables. It was virtually inevitable that India would be the last country to fully embrace renewables because of this, and so it is proving.
There have already been efforts towards mass roll outs of smart meters, although none anywhere near as drastic as this week’s. India’s government had already set the target of 250mn smart meters nationwide, although no time frame was given. In August 2019 it was announced that the EESL had successfully installed 500,000 smart meters across some Northern states as part of the Smart Meter National Program.