CableLabs CTO & SVP Belal Hamzeh has raised eyebrows and even more questions with his emphasis on adding computing power and virtualization to the industry’s baseline cable connectivity platforms, particularly given how Covid-19 has inhibited the group’s project Adrenaline progress.
Following up Hamzeh’s comments, CableLabs Principal Architect Randy Levensalor sought to slow the down pace somewhat. Speaking during the Cable Next Gen Europe Digital Symposium from Light Reading, he underscored how the addition of computing power and virtualization can occur in the headend, or in the hub, or in the node. CableLabs is already seeing the roll out today for headends and hubs, although Levensalor could not provide a ballpark timeframe for nodes, other than “getting pretty close” – so expect the industry to start ramping up here over next few years.
He did, however, tease that CableLabs has also worked with some companies using a GAP (Generic Access Platform) node to get compute close to the customer and even on the customer premises itself.
Some 18 months after work began on the Adrenaline virtualization project, divisions of opinion are beginning to emerge at vendors.
Head of Access Networks Business Development at Harmonic, Daniel Etman, started out by saying, “We all owe our careers to CableLabs,” before noting how the discussion on compute should not be dragged down the rabbit hole of application-specific hardware. “This is all about compute power with intelligent software on top, whether a virtual CMTS or virtual RAN,” he said.
Referring to Hamzeh’s mention of automation orchestration, Etman said, “I love that. From our perspective, we’ve done this and have massive deployments. We’re finding out that the amount of data mining from this is virtually unlimited, so it’s time to put that data to work and go to the next phase of networks which is about intent-based networking and proactive management; making the network alive. All these tools are important so it’s great that CableLabs is focusing on this. ONAP is another example of this, but we are not there yet.”
David Keane-Mirajkar, Regional VP at CommScope, partly disagreed with Etman. “There is a need to optimize compute power and scale, if we’re taking CMTS as an example here. Adrenaline takes us further down the route, but there are basic things to address first. I agree with the point about optimizing compute, but you have to be realistic, right? If you have compute power, this is not only about virtual CMTS anymore,” said the level-headed Keane-Mirajkar, again pointing to the mobile sector as being much quicker off the mark to embrace virtualization.
Keane-Mirajkar referenced an unnamed operator customer of CommScope that drove down the virtualization path simply because its existing business model wasn’t sustainable. “I think one of the key drivers of virtualization is extracting cost out of the business – for example monetization of bandwidth doesn’t grow incrementally with usage of bandwidth,” he added.
Once the Harmonic and CommScope execs had finished trading blows, we managed to get an operator viewpoint from the DAA and virtualization debate as a suitable follow on from last week’s Faultline coverage.
Tele2’s Anders Bloom, Senior Systems Architect for Broadband HFC Development, kicked off by getting all nostalgic. “Back in the good old days, you had one big box doing everything, and if it broke down, you needed to reset the entire box. Then the evolution came along with bigger boxes, adding more functionality like load balancing, but you still had the same problem if something happened to the box – you had to reset the whole thing and lose all the customers. Later on, we started to decouple the MAC and PHY which was a huge development at the time, but still required resetting the whole box. In virtualization, you can build a robust and rigid forwarding plane. If a function breaks, then you can just restart that function. If you want more development, then you can just connect to standardized APIs without touching the forwarding plane, so we see this as the natural evolution,” said Bloom, clarifying the clear cableco benefits in one short history lesson.
Providing a progress update, he said Tele2 has been successfully implementing virtualization and software-based CMTS for a couple of years now, replacing its previous monolithic software. The Swedish operator followed this move by beginning its DAA structure last year all the way down to premises, and the latest development has been to use the Kubernetes version – claiming somewhere between 50,000 to 70,000 customers are now on the Remote-PHY Device (RPD) version of its DAA using edge QAM architecture.